Totaling 380MW, multiple photovoltaic projects from Huaneng, Three Gorges, Datang, and other companies have been connected to the grid.


Release time:

2023-11-05

Multiple projects, including those from Huadian Group, Datang Group, and Three Gorges Group, have been connected to the grid, with a total capacity of 380 MW.

Huadong Shandong Yutai Photovoltaic Power Generation Project Grid Connection
 
On October 31, the inverters 1 to 10 of the No. 10 box substation of the Huadong Shandong Yutai photovoltaic power generation project were closed one by one, marking the full-capacity grid connection of the project's first phase of 70MW. The project is located in Yutai County, Jining City, with a planned capacity of 200MW, constructed in two phases, with the first phase having a capacity of 70MW. The project adopts a combination of fishery farming and photovoltaic power generation, creating a new power generation model of "power generation above and fish farming below". After the completion of this project, the annual power generation is about 80 million kilowatt-hours, and the annual utilization hours are more than 1000 hours.
Inner Mongolia Jinghai 100MW Photovoltaic Project Grid Connection
 
Learned from China Power Construction's official website, recently, the Inner Mongolia Jinghai 100MW photovoltaic project achieved full-capacity grid connection.
 
This project is one of the first batch of thermal power flexibility transformation supporting photovoltaic power generation integration projects in the Inner Mongolia Autonomous Region, and also one of the first batch of mining ecological restoration and photovoltaic power generation projects in Wuhai City. It is located in the Kabuqiu old Donggou coal mine goaf area in Haibowan District, Wuhai City, Inner Mongolia Autonomous Region, covering an area of 3855 mu. The project has a total installed capacity of 100MW, including 5 photovoltaic areas, 32 photovoltaic sub-arrays, and 8187 unit groups. It also includes a 110KV substation.
 
Yunnan Qiaojia Yangwotou 65MW Photovoltaic Power Station Grid Connection
 
On October 30, the Yangwotou 65MW photovoltaic power generation project in Qiaojia County, Yunnan Province, constructed by Three Gorges Yunnan Netou and jointly undertaken by China Hydropower Eighth Bureau, successfully achieved grid connection.
 
The Yangwotou project is located in Yaoshan Town, Qiaojia County, Zhaotong City. The project has a rated installed capacity of 65MW, covers an area of about 1500 mu, with a total investment of about 340 million yuan. The altitude of the project area ranges from 2960 meters to 3370 meters. It includes 24 fixed photovoltaic arrays and a newly built 220kv substation. The project started construction on March 2, 2023. After the completion of the Yangwotou project, it can supply about 97.3502 million kWh of green electricity to the power grid each year, saving about 29,400 tons of standard coal and reducing carbon dioxide emissions by about 81,000 tons annually.
 
Three Gorges Shengnong Guangze 45MW Distributed Photovoltaic Project Achieves Full-Capacity Grid Connection
 
On October 31, the first phase of the Three Gorges Shengnong Guangze 45MW distributed photovoltaic project achieved full-capacity grid connection.
 
The Three Gorges Shengnong Guangze 45MW distributed photovoltaic project is a demonstration project of "central and private enterprise" cooperation between the central enterprise Three Gorges Group and the private enterprise Shengnong Group. The project started construction in February this year and achieved the first batch of grid-connected power generation in March. This time, the first phase of full-capacity grid-connected power generation was achieved. After the initial commissioning, it can provide an average of 45.557 million kWh of clean electricity per year. Compared with thermal power plants with the same power generation capacity, it can save 14,000 tons of standard coal per year, reduce carbon dioxide emissions by 38,000 tons, sulfur dioxide by 7.3 tons, and dust by 1.5 tons, effectively ensuring the supply of clean, environmentally friendly, and low-carbon green energy.
 
Datang Pingluo Gaoren Phase II 100MW Photovoltaic Hybrid Power Generation Project Grid Connection
 
On October 31, the Datang Pingluo Gaoren Phase II 100MW photovoltaic hybrid power generation project was successfully connected to the grid. The project is located in Gaoren Township, Pingluo County, Shizuishan City, Ningxia Hui Autonomous Region, with a total installed capacity of 100MW.